Feeds:
Posts
Comments

Archive for the ‘Village Board’ Category

Demolition started this week on the east side of South Cook Street, north and south of Station Street. Demo work will continue through the rest of this week, and concrete forms for the new sidewalks and planter boxes will be set beginning next week (April 13). Installation of new sidewalks in Phase 1 is tentatively scheduled for the week of April 20. You may see the new sidewalk being poured back sooner, weather depending.

 

Phase 2 demolition work is tentatively scheduled to begin the week of April 27. Phase 2 includes the northwest corner of Cook and Station streets, the west side of Cook Street, south of Station Street, and the northwest section of Station Street alongside Nekter. The project manager will be around to coordinate with impacted businesses in advance of this work. 

 

The section of sidewalk on the south side of East Station Street (past the Barrington Flower Shop) will be moved from Phase 4 to Phase 1. 

 

The project phasing plan can be found here.

 

All impacted businesses and restaurants remain open! Your continued support during construction makes a big difference to our community.

 

To stay informed and receive project updates, please visit the construction updates page on the Village’s website.

Read Full Post »

Village of Barrington Hills board members (l-r) JC Clarke, Laura AB Ekstrom, Brian Cecola, Marsha McClary, David Riff and Jessica Hoffmann. Not pictured: Thomas Strauss.

Our Village Board of Trustees met Monday evening. This marked the third meeting since their December 2025 meeting when residents were blindsided to learn, “110 Acre AI data center campus pitched to Village Board.”

The first speaker Monday night expressed their continued dissatisfaction with the Board as follows:

“All right. Good evening. My name is Aaron Becker. By now you probably know who I am.

I’m speaking tonight in regards to the Village attorney’s letter in response to my questions from January 27th,and I’ve got a couple other comments as well.

I really appreciate the Village responding in righting to my quick response. However, I ask respectfully and directly why several of my explicit questions and requests were not answered at all. They were just omitted, so… .

The response explains why it believes its past actions were lawful, but it does not confirm whether any of the safeguards I requested would be implemented. My question tonight is simple: was the omission intentional?

In the Village Summer 2021 newsletter, residents were told by Trustee Ekstrom, she’s not here today, and I’m going to quote her, ‘Most residents know that they can attend the Village Board meetings, many may not realize that committee and commission meetings are also open to the public. Our Village is a community above all else and having input from our residents reflected in our decision making is not only welcome but encouraged.’

I’ll say this much, I genuinely appreciate that perspective and I believe her. With that in mind, here’s some feedback:

Please confirm that all off-record communications with Brennan Development Group will stop.

Please stop project specific merit discussions absent of formal filings.

Please confirm that unsupported tax claims will not be repeated by the Village without substantiation.

Please confirm that records will be preserved.

Please do everything in your power to maintain true independence of the Plan Commission.

I’d also like the Board to reflect on some of the statements Board of Trustees members have made in the past. In the same Summer 2021 newsletter, residents were told by Trustee Strauss that quote, ‘We live in a special community, and the Board is committed to maintaining our heritage.’

And Trustee Riff said, ‘I would like to make certain that we remain focused on the budget, protect our residential zoning rights (or rather zoning laws), and ensure that our community remains safe and secure for all residents.’

So those are strong words. And they matter. So I’ll ask each of you as Trustee members, do you believe that based on all of the emails we have now seen and read that you have honored those commitments? That you are protecting our residential zoning rights. And that you are maintaining our heritage as a Village.

I’ll be honest, I don’t. I read all the emails. I don’t believe it.

You have to go to bed at night. You have to look yourself in the mirror and say that you believe you’ve protected the residential zoning rights with your actions and your words.

My wife spoke last month about actions and words and holding people accountable when their actions and words don’t align. And that’s what we’re here doing asking of our leaders for continuity between their actions and their words.

That’s all I’m asking. When you say you’re going to do something, follow through and do it. Please.

So, to summarize, respond to the five requests I had in the letter either acknowledging you made a mistake and how you’re going to fix it, or that you made no mistake.

Either way we deserve clarity we deserve responses to those.

That’s my comment. Thank you very much.”

The audio recordings from the March 30, 2026, Board of Trustees meeting can be found here.

Related:Do you trust our Board of Trustees? We don’t. But you decide for yourself once we have finished. (Follow-up),” “Do you trust our Board of Trustees? We don’t. But you decide for yourself once we have finished. (Part 3),” “Do you trust our Board of Trustees? We don’t. But you decide for yourself once we have finished. (Part 2),” “Do you trust our Board of Trustees? We don’t. But you decide for yourself once we have finished. (Part 1),” “110 Acre AI data center campus pitched to Village Board

 

Read Full Post »

The Village Board of Trustees will be conducting their regular monthly meeting this evening beginning at 6:30 PM. Topics on their agenda include:

  • [Vote] Resolution Authorizing the Issuance of Notice of Award for the 2026 Road Program Project by the Village of Barrington Hills, Illinois Resolution 26 –
  • [Vote] Ordinance Approving a Final Plat of Subdivision For the Acorn Corner Subdivision – 11 & 12 Rock Ridge Road Ordinance 26 –
  • [Vote] Resolution of the Village of Barrington Hills in Support of Municipal Housing Authority Resolution 26 –
  • Register Now: Land We Love Run 5k/10k Celebrating America250 on June 28 2026

A copy of their agenda, including info on listening to the meeting, can be viewed and downloaded here.

Read Full Post »

Friday, South Barrington Village President Paula McCombie shared this in one of her weekly updates to residents:

“As I have reported in previous emails, the upcoming Barrington Road Widening Project will soon get underway. The first step is tree removal, which will begin along Barrington Road between Algonquin Road (IL 62) and Central Road within the next couple of weeks.”

Since we were unfamiliar with the project, we’ve learned this:

“Improvements to Barrington Road relieve congestion and reduce the risk of crashes.

Updates to Barrington Road provide two additional lanes of traffic in each direction separated by a median between Mundhank Road and Algonquin Road. Ardmore Roderick, selected as the prime consultant, leads Phase II engineering services for this transformative project, ensuring that the design and execution of improvements advance the infrastructure and serve the community’s needs.

As the lead firm, Ardmore Roderick is responsible for preparing plans, specifications, and estimates for the road between Illinois Route 62 and Central Road. A new shared-use path fills a gap in Chicago Metropolitan Agency for Planning’s regional trail system.

Additional improvements modernize and replace traffic signals throughout the corridor and replace the box culvert structure carrying Barrington Road over Poplar Creek. During the Phase II design process, Ardmore Roderick collaborated with the design team to incorporate a pile-supported embankment that strengthens soil stability, realigned the roadway to improve safety, and incorporated walls at strategic locations.”

A brief  project description can also be found here.

Buckle up.

Read Full Post »

When the weather conditions permitted, construction activity continued through the winter months. Between January and March, crews completed the following work:

Preparation for permanent sheeting installations
Permanent sheeting installation is required along the Route 14 corridor to support excavation and construction of the lowered roadway. Following excavation work, concrete formwork will cover the sheets, completing the final retaining wall structure. The contractor has completed pavement removal and surface preparation, positioning the start of this permanent sheet work this spring.

Ongoing construction of the storm sewer pump station
Following substantial completion of the pump pit structure last year, work on the pump station has continued through the winter. Activities included installing stairs and handrails, placing drains, removing concrete formwork and backfilling, applying waterproofing, retaining wall work, installing electrical conduit, and structure preparation and construction of masonry walls. For more information on the pump station, please refer to the December 2025 update.

Water Main and Storm Sewer Installation
Elevation changes associated with the lowering of Route 14 necessitate the rerouting of some existing Village utilities and installation of new facilities. Earlier this year, crews completed storm sewer and water main relocation work on Route 14 near Drury Lane. They also began installing additional storm sewer infrastructure to drain the future underpass, which will connect to the pump station structure.

Route 14 Culvert Construction
As part of the project, Flint Creek will be relocated to maintain gravity flow. Currently crossing under Route 14 just west of the railroad tracks, the creek will be shifted farther west toward Route 59, where it will flow beneath Route 14 through a new storm sewer culvert. Construction of this culvert is underway, with excavation work completed and forming and rebar placement work underway. The culvert’s bottom slab will be formed and poured first, followed by the walls and top of the structure. After completion of this work, a similar structure will be constructed to carry the creek under Route 59.

Continued relocating utilities
Utility relocation work has continued throughout the winter and will progress alongside upcoming construction activities.

Weather and material availability permitting, the contractor plans to begin sheeting and excavation work necessary to begin construction of the railroad bridge this month. As this work progresses, the contractor will refine plans for the remainder of this year.

To stay informed and receive project updates, please visit the dedicated project website us14underpass.com or watch for email notifications.

Read Full Post »

By Michelle Meyer | Shaw Local

A ramp connecting the Jane Addams Memorial Tollway to Route 31 in Elgin will be closed for toll plaza improvements starting Sunday and is expected to last through the summer.

Beginning at midnight Sunday, the ramp connecting westbound Interstate 90 to southbound Route 31 will be closed, according to an Illinois Tollway news release. A posted detour will direct traffic on the interstate to the Randall Road interchange, bringing cars back onto eastbound I-90 to access Route 31.

“Tolls will be waived at the Elgin Toll Plaza for traffic following the detour,” officials said in the release.

Crews will be removing the existing barrier walls and equipment and installing new infrastructure. Ramp pavement and shoulder work, along with improvements to electrical, lighting and signage, also are planned, according to the release. All work is weather-dependent.

The construction is part of Illinois Tollway’s 16-year, $15 billion capital program called Move Illinois and its seven-year, $2 billion Bridging the Future capital plan. Improvements are planned for all toll plazas systemwide.

Signs warning about the upcoming closure will be posted this weekend. Updated information will be posted on the Illinois Tollway website’s daily construction alerts.

Maps and construction information are available in the “projects” section on the tollway website.

Article continues here.

Read Full Post »

Erin Chan Ding posted the following to her Facebook followers Tuesday:

While Chan Ding claims to be ‘honored’ to continue her service on the Barrington 220 Board of Education, her actions during her failed primary campaign suggest she has forgotten who she truly serves.

By using District resources to fuel a partisan run—earning her an official ethics sanction—and subsequently accepting campaign donations from the very union whose contracts she must impartially negotiate, she has created a profound conflict of interest.

Most disappointingly, she has let down the constituents who elected her on the fundamental promise of nonpartisan leadership. A school board seat is a sacred trust meant for the advocacy of students, not a political steppingstone.

To treat the Board as a ‘consolation prize’ after a partisan defeat, while carrying the weight of these ethical breaches, is a disservice to every voter who expected her to put our schools above her own political ambitions.

Related:Chan Ding, Teachers Unions losers in IL 52nd District Primary Election,” “New Evidence of Chan Ding’s Policy Violations and Conflicts of Interest,” “Candidate Erin Chan Ding’s opinion on Data Centers,” “Barrington area Democrats condemn Chan Ding mailers,” “The D220 Board of Ed gets another ‘F’ in accountability & transparency,” “School district’s parking plan defies logic,” “Zoning change defies village policy,” “The Real Issue in Barrington 220 Isn’t Parking or Levies — It’s Leadership Culture,” “Change.org Petition: ‘For the Resignation of Erin Chan Ding ~ D220 Resources are Not for Political Campaigns’,” “BOARD OF ED VOTES, MEMBER CHAN DING MADE FLAGRANT POLICY VIOLATIONS – Part 2,” “BOARD OF ED VOTES, MEMBER CHAN DING MADE FLAGRANT POLICY VIOLATIONS,” “Erin Chan Ding: The violations just keep piling up…,” “Erin Chan Ding starring in another episode of, ‘Rules For Thee But NOT For Me…’,”  “District 220’s Lack of Transparency (Updated),” “District 220’s Lack of Transparency,” “Ding Politicking on School District Property,” “Dual School Board and State Rep Positions Legally Incompatible,” “D220 Abuses Taxpayer Funds in favor of Partisan Campaign,” “Ding In Her Own Words – CONFLICTED!,” “Ding Doubles Down,” “Ding’s D220 Deception,” “Chan Ding running in Democratic primary in 52nd,” “Three (3) Democratic candidates queued to run for the IL 52nd District House seat in 2026

 

Read Full Post »

The Village Roads & Bridges Committee meets this afternoon at 4 PM. Topics on their agenda include:

  • [Vote] Road Program 2026 Recommendation (Left blank)
  • River/Algonquin Road Curve

A copy of the full posted agenda can be viewed and downloaded here.

Read Full Post »

The Equestrian Commission/Riding Club will be meeting this evening at 6:30 PM. Topics on their agenda include:

  • McHenry County Conservation District’s Comprehensive Plan
  • Animal Disaster Preparedness Plan, and
  • Equestrian Signage

A copy of the agenda can be viewed here.

Read Full Post »

There was no mention of the data center discussions which began in October in President Cecola’s quarterly Village Newsletter distributed last week. So much for transparency.

Last week we published a series of editorials to enlighten residents on the, “110 Acre AI data center campus pitched to Village Board.” We referenced Freedom Of Information Act (FOIA) records we obtained, and several people have asked if they might obtain a copy.

Those records we were provided, edited only to eliminate redundancy such as multiple copies of the “Data Center Overview,” can be found here.

Related:Do you trust our Board of Trustees? We don’t. But you decide for yourself once we have finished. (Part 3),” “Do you trust our Board of Trustees? We don’t. But you decide for yourself once we have finished. (Part 2),” “Do you trust our Board of Trustees? We don’t. But you decide for yourself once we have finished. (Part 1),” “7 things to know about Illinois data centers,” “Data Center group concerned over pause,” “110 Acre AI data center campus pitched to Village Board

 

Read Full Post »

Older Posts »