Feeds:
Posts
Comments

Archive for the ‘Road construction’ Category

Overnight ramp closures and detours are scheduled this week on westbound I-90 at the Barrington Road and Route 59 interchanges due to ongoing Illinois Tollway plaza improvements.

Schedule & Detours

Westbound I-90 to Barrington Road Ramp:

  • When: Tuesday, November 17 (8:00 PM to 5:00 AM Wednesday), for two nights of electrical work.
  • Detour: Routed via Route 59 and Route 72.

Westbound I-90 to Route 59 Ramp:

  • When: Thursday, November 19 (9:00 PM to 5:00 AM Friday) for new tolling equipment installation.
  • Detour: Exit at Beverly Road, go north to Route 72, then east to Route 59.

 

Read Full Post »

Over the past month, crews have coordinated the following work:

  • Railroad bridge construction.Crews substantially completed the north bridge abutment (the structural element at each end of a bridge) and have poured the concrete for the center bridge pier. Following curing time and removal of formwork from these two areas, sheeting and excavation work for the south bridge abutment will begin later this month.
  • Storm sewer installation.Crews installed a substantial section of storm sewer along Route 14 between Hough Street and Shorely Wood Properties, which will convey stormwater from the bottom of the underpass to the Illinois Department of Transportation storm sewer pump station to keep the roadway dry in inclement weather.
  • Continued work on the storm sewer pump station.With building work largely complete, crews continue with electrical and HVAC work to support the facility.
  • Route 59 culvert construction, a storm sewer that will carry the relocated Flint Creek beneath the roadway.Crews completed the western half of the Route 59 culvert. The culvert has been backfilled to prepare for installation of curb and roadway base material next week, followed by paving and striping work in mid-November. Once this work is complete, the contractor will coordinate a change to the traffic pattern, shifting traffic onto the west side of Hough Street and closing the east side, which will allow for the second half of the culvert to be constructed this winter.
  • Initiated access drive work at Shorely Wood. Crews began demolition and grading work to support a new Shorely Wood entrance drive location. Permanent paving work will be coordinated within Shorely Wood over the next few weeks. Traffic will shift to the new access location following this final paving work and the installation of a temporary drive extension to the temporary Route 14 roadway. This traffic shift is currently anticipated to take place before Thanksgiving.

Alerts will be shared ahead of any changes to traffic patterns, along with revised traffic pattern visuals.

To stay informed and receive project updates, please visit the dedicated project website us14underpass.com or watch for email notifications.

 

Read Full Post »

It’s Election Day, 2026. We’re asking everyone to vote for the following with good reasons:

Our reasons to vote for Darby and Marty include:

Information on where you are registered to vote today can be found here.

PLEASE VOTE!

Read Full Post »

Per the Village of Barrington Hills website:

“The Cook County Department of Transportation and Highways (CCDOTH) has notified the Village of Barrington Hills of upcoming resurfacing work on Old Sutton Road, a County-maintained roadway, between Dundee Road and County Line Road.

This Cook County project may begin as early as Monday, October 26, 2026.

Anticipated Construction Schedule

Weather permitting, the construction, being completed by Builders Paving is expected to proceed as follows:

  • Week of October 19: Installation of construction signage
  • Week of October 26: Installation of new lateral pipe culverts and hot-mix asphalt (HMA) patches over the culverts
  • Week of November 2: Milling of existing pavement
  • Week of November 9: Placement of new asphalt surface course
  • Week of November 16: Installation of permanent pavement markings and reflectors, and culvert cleaning

Traffic Impacts and Access

One lane of traffic will remain open during daytime construction activities, with flaggers directing motorists through the work zone. Both lanes will reopen during non-working hours.

Access for residents and emergency vehicles will be maintained throughout construction. However, motorists should anticipate potential delays and allow additional travel time when traveling through the area.

Project Questions

Cook County is responsible for managing this roadway improvement project. Residents with questions or concerns about the work should contact Cook County’s project representative, Brian Cameron, at Brian.Cameron@mbakerintl.com.

The Village of Barrington Hills appreciates Cook County’s investment in improving our local roadways and thanks residents for their patience and cooperation during construction.”

Source

Read Full Post »

Per Cuba Township Facebook Post:

“Road work is slated to occur at the intersection of Plum Tree and Route 14 from Monday, Oct 26 to Wednesday, Oct 28. Please find the attached road map to indicate where flaggers and road work will be.

It is highly suggested that during this roadwork, it will be best to completely avoid the intersection if at all possible.

If you must take this route expect heavy delays”

Read Full Post »

CHICAGO – The Illinois Department of Transportation announced today that culvert repairs at the intersection of Illinois 59 and Dundee Road (Illinois 68), in Barrington Hills, will begin, weather permitting, Wednesday, Sept. 30. ​

To complete the work, daytime lane closures will be required approaching the intersection. At least one lane will remain open in both directions during the construction. ​

The project is anticipated to be completed in November.

The public can expect delays and should allow extra time for trips through this area. Alternate routes are encouraged. Drivers are urged to pay close attention to flaggers and signs in the work zones, obey the posted speed limits and be on the alert for workers and equipment.

Over the next six years, IDOT is planning to improve 7,107 lane miles of highway and 8.4 million square feet of bridge deck as part of Rebuild Illinois, which is investing $33.2 billion into all modes of transportation. Accomplishments through Year Seven of Rebuild Illinois include $25.6 billion of improvements statewide to 24,498 lane miles of highway, 959 bridges and 1,475 additional safety improvements.

For more information on IDOT projects, click here. Find traffic and road conditions at www.gettingaroundillinois.com. You also can follow IDOT on Facebook and X.

# # #

Read Full Post »

Over the past two months, crews have coordinated the following work:

  • Railroad bridge construction. Crews completed the footing for the north bridge abutment (the structural element at each end of a bridge) and are nearing completion of formwork for the northern bridge wall, which will begin being poured before the end of the month. Crews completed sheeting and excavation work for the center bridge pier and have begun installation of the sheet pile foundation at the center pier location.
  • Storm Sewer Installation. Crews began installation of the storm sewer, which will convey stormwater from the bottom of the underpass to the Illinois Department of Transportation storm sewer pump station to keep the roadway dry in inclement weather.
  • Continued work on storm sewer pump station. With building work largely complete, crews continue with electrical and HVAC work to support the facility.
  • Initiated Route 59 culvert construction, a storm sewer that will carry the relocated Flint Creek beneath the roadway. Crews installed traffic control, which allows for the west half of this storm sewer structure to be constructed. Ahead of culvert work, sanitary sewer and water main relocations were completed in this location, and sheeting was installed along the roadway centerline to allow for adjacent excavation work. Excavation is now underway, to be followed by the forming and pouring of the bottom slab of this new storm sewer culvert.

As the contractor continues the Route 59 culvert work as shared above, the current traffic pattern outlined below will remain in place to facilitate this work.

  • A temporarily shortened northbound left-turn lane from Hough Street onto Route 14.
  • Temporary closure of Lions Drive at Hough Street. Barrington Park District visitors can still access Lions Drive from Route 14.

The contractor is working to consolidate construction stages and complete the west half of the Route 59 culvert as part of ongoing work in this area. They are targeting completion of the west half of the culvert near the end of October, followed by roadway restoration work. Currently, we anticipate shifting traffic onto the restored western half of Hough Street and reopening access to Lions Drive ahead of Thanksgiving.

To stay informed and receive project updates, please visit the dedicated project website us14underpass.com or watch for email notifications.

Read Full Post »

A Canadian National freight train stops traffic along U.S. Route 14 on Aug. 6, 2026, in Barrington. An underpass is being constructed at this location to allow traffic to flow better. The underpass is expected to be completed in late 2027. | Stacey Wescott/Chicago Tribune

By John Lippert | For the Chicago Tribune

When Karen Darch started agitating in 2007 for an underpass so U.S. Route 14 can pass beneath the Canadian National railroad tracks in Barrington, she had six children and no grandkids.

Nineteen years later, as workers are shattering the affluent quiet of her suburban street by pounding retaining walls for the underpass into place, she has seven grandchildren.

Darch says she can’t say how many grandchildren she’ll have when the half-mile, $94 million underpass is finally complete, hopefully by the end of next year.

But now, Darch is confronting a problem that could aggravate her grandchildren for decades to come.

That problem is a new round of mergers that’s putting the ownership structure of North American railroads through a blender and triggering a prolonged period of tension and uncertainty.

Union Pacific, in tandem with its $85 billion takeover bid for Norfolk Southern, has agreed to start running more trains over Canadian National’s suburban Chicago network. At the outset, this will include rerouting some trains now running through inner-city Chicago.

Former Barrington Village President Karen Darch stands near construction for the new U.S. Route 14 underpass on Aug. 6, 2026, in Barrington. Darch spent years seeking solutions like this underpass to rail-induced traffic problems. The underpass will be routed under freight train rails where currently traffic gets blocked several times a day. | Stacey Wescott/Chicago Tribune

Darch, an attorney who served as Barrington’s village president for 20 years until last year, says she believes that sooner or later, the railroads will build a second freight track through Barrington, a suburb 35 miles northwest of Chicago. That’s because Canadian National has already spent years double-tracking the line to within 10 miles south of Barrington, she said.

In theory, rail experts say, this second track could mean dozens of additional Canadian National and Union Pacific freight trains rolling each day through downtown Barrington at 40 miles an hour, up from 20 currently.

That’s in addition to the  50,000 cars and trucks that converge on Barrington each day, and 800 daily school bus trips. Barrington also attracts 70 Metra commuter trains per day. Each of these blocks the main north-south and east-west streets through downtown for a few minutes as passengers come and go.

“If they build another track, there’s going to be a much greater impact than we’re feeling now, so more has to happen in response. We may need another underpass, or maybe two other underpasses,” said Darch in an interview last month. “And a greater portion of the funding should come from businesses that are benefiting from traveling the rail.”

Report continues here.

Read Full Post »

By Steve Zalusky | Daily Herald

Barrington officials are celebrating the completion of phase one of the village’s downtown streetscape project, which they hope will boost the town center as a regional attraction.

The $1.5 million project included replacing deteriorating sidewalk pavers with new concrete and clay brick accents, and resurfacing and restriping aging streets.

New landscaping includes flower beds and planters bursting with color.

“From the beginning, our goal was to create a downtown that is more beautiful, accessible, welcoming and easier to maintain for years to come,” Village Manager Scott Anderson said.

Village President Mike Moran noted the work also creates expanded outdoor dining spaces (but not parking) for businesses such as Cook Street Coffee and Gigi Wine Bar and Bistro.

Article continues here.

Read Full Post »

The Village Board of Trustees will be conducting their regular monthly meeting this evening beginning at 6:30 PM.

The only item of significance on their agenda appears to be recognition of William Walsh for 33 years of service. A copy of their agenda, including info on listening to the meeting, can be viewed and downloaded here.

Read Full Post »

Older Posts »