The Cuba Road Bridge reconstruction project update followed and brought news of further delays.  Dan Strahan, Village Engineer, reported that the contractor on the project requested the deadline for completion of the bridge be extended due to an error on their part with “shop drawings” and a change in steel support materials. 

Both IDOT and the Village refused an extension, and depending on how far beyond the original final date for completion it takes to reopen the bridge, IDOT and the Village will likely get monies back in the form of penalties deducted from the final invoice.  The contractual deadline for completion is August 7th.

When Strahan concluded his report, Chairman Cecola remarked that he expected he would be receiving calls from residents regarding what seem like undue further delays.  The discussion of the further Cuba Road Bridge SNAFU’s can be heard here.

Updates on the 2016 road programs, including pavement markings for some roads, patching of Ridge Road, drainage issues and the planned roadwork on Helm, Healy, River and Woodcreek Roads, as well as Lakeview, Hawthorne and Tamarack Lanes were then discussed.

Trustee Cecola, who also oversees public safety, concluded the meeting with some comments on recent vehicular accidents in the Village, including one involving one of our officers, and his praise of how our officers have responded to these unfortunate occurrences.  His remarks can be heard by clicking here.