Temporary Route 14 Closure Update: Progress is Happening!

It has been a busy couple of weeks on the ground as we work toward opening up the temporary four-lane Route 14 roadway and the temporary two-lane Lake Zurich Road. Here’s what’s been happening behind the scenes:

What’s still to come?

As a result of ongoing utility relocation and the more manual track-building process being utilized by CN, the expected opening is now anticipated by the end of October, weather permitting. All parties are working hard to get everything ready and are exploring ways to open things even earlier, if possible.

Thank you for your continued patience and support of all Barrington businesses during this time.