U.S. Route 14 Underpass Update

Construction activity has continued since Route 14 reopened on its new temporary four-lane roadway at the end of October.

Over the past month, crews have completed the following work:

Weather and material availability permitting, the contractor plans to begin excavation and installation of the Route 14 culvert over the next month, along with continued construction of the pump station. As utility relocation progresses, the contractor will refine plans for early next year. Upcoming work is expected to include the following: preparation for retaining walls, additional utility installations, and construction of the railroad bridge structure.

To stay informed and receive project updates, please visit the dedicated project website us14underpass.com or watch for email notifications.