“CONSTRUCTION UPDATE November 17, 2022
The concrete patching taking place at the intersection of Lake Cook Road and Northwest Highway is part of the Main St resurfacing project being completed by the Illinois Department of Transportation (IDOT).
The overnight lane closures in place right now are necessary due to the nature of the concrete patching process. IDOT has indicated that the open patches will be poured either tomorrow, Friday 11/18 or Saturday 11/19.
They will continue with removals early next week and aim to reopen the entire intersection on Wednesday 11/23 before the Thanksgiving holiday weekend.
There will be another round of patching the week after Thanksgiving but this is expected to be completed by the end of the week, Friday 12/2.”